Imam Khomeini Refinery Expansion Project - Shazand, Arak

Imam Khomeini Refinery Expansion Project - Shazand, Arak

Project Info

Contract Type:

EPCC

Project Duration:

45 Months

Client:

National Iranian Oil Engineering & Construction Company (NIOEC)

Project Overview

  • Integrated EPCC execution of the refinery expansion program at Imam Khomeini Oil Refining Company (Shazand), aimed at capacity increase, product upgrading, and environmental compliance enhancement.

 

Scope of Work

  • Process design and detailed engineering
  • Global sourcing and procurement of critical equipment and materials
  • Construction and installation
  • Pre-commissioning execution and commissioning support

 

Project Objectives

  • Full compliance with environmental regulations
  • Daily production of 3 million liters of 100-octane premium gasoline
  • Reduction of fuel oil output and conversion into higher-value products
  • Increase gasoline production capacity from 4.6 to approximately 16 million liters per day
  • Increase in overall refinery capacity from 170,000 to 250,000 barrels per day
  • Upgrading all refinery products to meet Euro 5 international quality standards

 

Capacities After Completion

  • Gasoline: 16 million liters per day
  • Diesel: 10 million liters per day
  • Kerosene: 6 million liters per day
  • Fuel oil: 2 million liters per day
  • LPG: 21,000 barrels per day
  • Propylene: 7,000 barrels per day
  • Bitumen: 6,000 barrels per day

 

Project Highlights

  • Daily gasoline production reaching 16 million liters
  • Installation of 1,708 tons of major equipment
  • First refinery in the country equipped with a propylene production unit
  • Construction of 13 large-scale reactors ranging from 650 to 1,350 tons
  • Installation of the country’s heaviest integrated equipment: 1,470-ton Regenerator Reactor
  • Fabrication and erection of a 1,000-ton C3 Splitter column (100 m height, 6 m diameter)
  • Full compliance with Euro 5 environmental standards
  • Recognized in 2013 as a National Mega Project Award Winner