Construction of Two Crude Oil Desalting Units - Parsi & Aghajari Oil Fields

Construction of Two Crude Oil Desalting Units - Parsi & Aghajari Oil Fields

Project Info

Contract Type:

EPC

Project Duration:

30 Months

Client:

National Iranian South Oil Company (NISOC)

Project Overview

  • Execution of an EPC contract for the construction and upgrade of crude oil processing facilities in the Parsi & Aghajari oilfields, with a focus on increasing sour crude treatment capacity and modernizing production infrastructure.

 

Scope of Work

  • Process design and detailed engineering
  • Procurement and supply of required materials and process equipment
  • Construction and installation

 

Project Objectives

  • Rehabilitation and capacity enhancement of production headers and installation of two-stage separators (Stages 2 and 3) at the Parsi-dareh production unit, along with associated facilities such as pump stations, chemical injection systems, and a dedicated 24.5 km pipeline for segregated transfer of sour crude to the Karanj production unit
  • Refurbishment and capacity enhancement of headers at the Parsi Cluster wells following first-stage separation
  • Upgrading of inlet headers and installation of two-stage separators (Stages 2 and 3) for sour crude at the Karanj production facility
  • Construction of two desalting units, each with a capacity of 55,000 barrels per day, resulting in a total processing capacity of 110,000 barrels per day